Optimal Placement of Reclosers to Minimize Power Losses during Non-Load Bearing Disturbances in a Power Distribution Using Firefly Algorithm

Abstract

The research reported in this paper focuses on non-technical power loss reduction for power distribution systems. Such reduction of costs of energy not served (ENS.COST), is intelligently evaluated and optimized using a firefly algorithm, from where savings of 43.3% on energy not served are achieved.

Share and Cite:

Amolo, W. , Musau, P. and Nyete, A. (2021) Optimal Placement of Reclosers to Minimize Power Losses during Non-Load Bearing Disturbances in a Power Distribution Using Firefly Algorithm. Journal of Power and Energy Engineering, 9, 63-75. doi: 10.4236/jpee.2021.95004.

1. Introduction

Apparently, power distribution undergoes recurrent power outage due to transients and needless to say, consumers decry economic losses as a result. Notably, the situation is pegged on lack of metering facilities, unlawful tapping of power and fraudulence in the industry among others. The fact still remains that keeping quality and stability in power system needs among other things a huge amount of capital investment for its protection. Lack of proper protection amasses to power losses and the credibility of investments fails to prove its worth. The semi-conductor energy controlling mechanism (SCECM) replaced common electromagnetic circuit-breakers in distribution of energy against the effect of various loading [1] [2] [3]. This practice had the resulting rewards: Advanced stable variables; the application of the recovery plan was more innovative than before; low number of mathematical calculations and internetworked enactment was possible. To restore stability in distribution of power system, where data on transients has deficiency, reclosing technique with adaptive formulation is applicable [4] [5] [6] [7]. Microchip-based electrical relay and reclosers for data keeping are utilized in the energy distributing section on overload currents and disturbances. A multi-objective approach combining “energy amounts” and “reliabilities in communicating channels” was used in another invention to position reclosing device by means of the genetic-algorithm code (GAc) [8]. The first objective-function comprised of recloser cost outlays and the latter was for reliability status of the system. In general, a flowchart with optimization, numerical integration, with randomness to solve problems was modelled to handle random errors. This model was able to provide line (KVA * t) power with momentary failure. It has been shown that rigorous measures can be used to develop four placement methods of reclosers for optimal operation [2] [3] [9] [10].

Among the reviewed works in this research include [5], who developed a detection of theft of electricity (TOE) at various check points. Fraudulent behaviour among the consumers could then be put under check and non-technical power loss monitored. This was possible through a software applying database analysis and deciding on fraudulent cases. [11] described a proposed programmable recloser logic that when programmed would reduce protection time, detect upstream conductor slap and provided timely lockout. More still could detect fault location in a non-communication loop. [12] proposed analytical hierarchy process method (AHP) to analyze the system losses in distribution systems. This technique could minimize non-technical power losses through alteration of network topological arrangement. [11] employed probability based or Monte Carlo method of setting reclosers along power system distribution. The method exclusively provided a means to optimally place reclosers at intervals, making them operate at various optimal timings at various protection zones. More importantly the proposed method had the ability to determine an optimal reclosing cost benefit analysis for power quality and protection efficacy. [13] designed an intelligent fault location and detection technique along the power transmission lines. Electromagnetic induction effect was the principle applied to detect faulted point along the transmission line. GSM was used to remotely relay real-time information. [14] [15] came up with a piloted scheme that used smart switches combined with sectorized distribution feeder recloser technology. This method managed to lower the affected number of end users during power outages resulting from transient faults. This method applied current-time-curve to determine reaction time of reclosers.

Regardless of the various developments in this topic, non-technical power losses still are dragged on reliability concept as though it as a solution. More if not all energy production managers might choose to shut down just because electricity theft and its damage is alarming. Transformers are short circuited and high currents endanger those who are culprits. The most affected areas such as slum dwellings may begin to go without power.

This work improved the reclosers’ response period capability, providing its finest placement within the system distributing energy during transients. The study achieved an untroubled power distribution system and balance in the midst of transient conditions. Thus, 43.3 percent utility savings during operation of reclosers is achieved. Increased financial savings would increase investment and boost long-term productivity. Power producers would ultimately reduce the cost of power charged to consumers. Some of the consumers who will benefit are those who steal electricity because now they will pay for what is affordable. Meanwhile, more alarming state that’s addressed in this work is outages caused by interruptions from those who steal by using illegal connections. This work is shedding light on how the menace can be technically controlled even though it is outright non-technical. Reliability improvement of power distribution system has been addressed sufficiently if not completely. The Kenyan utility company shut down their power transformer owing to unlawful connection in Kibera, a slum area in Nairobi City. This happened on 24th August 2019, according to Kenya News Agency (KNA). Optimal reclosing that focuses on minimizing illegal power connections losses requires an intelligent approach which is applicable to transients. Reclosing cycle model (RCM) formulated using firefly algorithm is planned for this work. The problem formulation is based on ideal reclosers’ location, in electrical energy distributing network.

2. Formulation of the Problem

2.1. Problem Definition

A number of considerations were made for problem formulation featured separately hereafter, targeting the following operational issues:

1) Brief shut down improved in several ways, including the following:

a) Reduce faults—such as power tapings, tree lowering, tree fall, creatures’ movements, arresters, tour duties, and so on;

b) Reclosing quickly;

c) Reduce the number of consumers’ disturbance by using downstream recloser.

2) Distribution Line Reclosers

In this kind of recloser arrangement, the strategy is to minimize recloser time because it is based on the time delay required to extinguish the fault. Table 1 provides an overview of how recloser types and set-up work together with reclosing schemes. These standard ratings were important to guide all sectors of power systems.

The reclosing technique design was meant to have at most three delays. For all types of reclosers the power fault condition completely would have subsequent opening and closing the affected area three times to check whether the fault was able to clear itself. It is only the permanent faults, which normally open or cut off after the third delay to safe guard the power system apparatus. The time values provided are considered to be within the minimum accepted range for the purpose of setting a recloser depending on criteria applicable to the designer.

Table 1. Recloser schemes (IEEE Practices).

Firefly MATLAB coding for this work uses instantaneous values of 15 sec for period B and 30 sec for period C. These are time delays meant to safeguard especially transformers from stressing currents which are abnormally very high during transients.

2.2. Non-Technical Loss Reduction

Considering the costs incurred in an event that transient and permanent faults or “non-technical power occurs”. The objective cost function of transient faults were calculated as (1)

w ENS = min r = 1 n P r T r C r (1)

where C r , P r and T r are load based cost of energy, consumed power and recovery period in seconds during short-lived failures. C r is subject to recloser settings and brief power cut off caused by the operation:

2.3. Electricity Consumption

This model aims to reduce the cost and increase the system reliability with recloser’ optimization model given by Equation (2). This equation describes amount of power transferred during a blackout in a distribution network.

E h = 0 9 kVA I t r = P t (2)

In which, t r is operation time of the recloser, P is transferred power and E h , kW sec of the lost supply. kVA t r is the thermal energy required to melt a specific fuse element; taken as recloser dead-time. Using reclosing philosophy as shown in (3)

ENS = kVA t 1 + 0.01 kVA t 2 + 0.06 kVA t 3 (3)

where ENS is Energy not served during reclosing operation.

kVA = Transformer rating or size, t 1 , t 2 and t 3 time interval for reclosing period. The work aimed at optimizing savings in cost of energy, according to formulation in Equation (4)

min f ( x ) = E N S = d i t 1 + 0.11 d i t 2 + 0.06 d i t 3 (4)

where,

d i = D j F k L m R ( t ) C C r (5)

subject to;

0.5 t r 45.9 ;

75 D j 400 ;

0 F k 1 ;

R ( t ) R 0

In which Di is upstream supply for the model nine zones, Fk is rate of failure over the length of line, Lm is downstream length of line, tr fault clearance time based on recloser operation in 3 shots, C is accumulated recloser cost of operation and maintenance, Cr is cost of blackout per Kilowatt while R(t) is the rate of failure.

2.4. Operation and Maintenance Cost

Considering single recloser device, the total everyday device operation and maintenance cost is given by:

C r o m = ξ CENS (6)

ξ CENS = min ( f ( C r o m ) ) (7)

R ( t ) R 0 (8)

ENS max ENS ENS min (9)

In which CENS is unserved energy cost resukting from reclosing operation as a protective measure for feeders. Thus R(t) is the probability of success (reliability) index of a distribution system, under a given recloser constraints. R0(t) is the occurrence or reliability index projection compels, hence the location based energy savings realized according to the formualtion for the radial network.

2.5. Vector Parameters

Parameters in the vector settings included power, current, distance and time. These parameters are equated such that: x1 is per kilometer detection period, based on standard setting of the recloser x2 is downstream length of line in kilometer. And x3 is upstream length of line in kilometer. The per kilometer detection period along feeders is approximated as two second per kilometer. Parameters in the vector i.e. power, current and time are set and equated as;

x 2 = i = 1 9 L i (10)

x 3 = i = 1 9 L j (11)

L i = 5.6 , 7.4 , 10.4 , 13.2 , 16.7 , 19.9 , 22.5 , 24.5 , 26.1 (12)

L j = 26.1 , 25.4.22.5 , 19.9.16.7 , 13.2 , 10.4 , 7.4 , 5.6 (13)

g 1 = x 2 / ( x 2 + x 3 ) x 1 (14)

where g1 is time taken to locate fault, while x1 is standard setting for detection period, i.e. two seconds per kilometer. Equation (14) shows feeder’s switching time. Post fault switching period for individual feeder is given as per Equation (15) while Equation (16) illustrates period taken to clear faults. Demand based un-served energy during the blackout is shown in Equation (17) and the Per kVA, per zone rate of failure is given by Equation (18), In which D is downstream demand. Protective equipment cost of maintenance and operation is formulated in Equation (19) and the cost savings for unserved demand modeled as shown in Equation (20)

g 2 = g 1 + 15 s (15)

g 3 = g 2 + 30 s (16)

C r = $ 1 / kVA (17)

g 4 = g 1 D + 0.11 D g 2 + 0.06 D g 3 (18)

g 5 = 0.008 D (19)

g 6 = $ 0.008 / kVA (20)

CENS = min ( C r ( g 1 g 2 g 3 g 4 g 5 g 6 ) ) (21)

The limits for these vector parameters include:

0.5 x 1 45 ; 80 D 1800 ; 0 g 5 1 and 1 x 3 26

ENSmax is the highest outage and expressed by considering the recloser operation in terms of fault location time, which is given by;

Faultlocationtime = x 1 / x 1 + x 2 Reclosersettime

where, x1 and x2 are downstream and upstream distances to the faulted area. Fault location is the place where a short circuit current occur. The distance is measured from the sub-station recloser position. Fault location time for faulted area was calculated using Equation (13).

3. Methodology

Intended reclose operation is optimized via FA, minimizing un-served-energy, according to formulated problem in Section 2. Process of mitigating Recloser for reduction of outage costs (9), is considered. Types of fault and faulty area are defined by setting parameters. Numerical results are achieved through applicable irregular testing based on computation, solved by FA, factoring in vulnerabilities of reclosing operation (13).

3.1. FA’s Classical Pseudo Code

Step 1: Initialization of algorithm parameters.

Step 2: Creation of first population using: X j , i = X j . i L + rand ( X j , i U + X j , i L )

(In which j and i are integers ranging from 1 to n and N respectively i.e. count of decision variables).

Step 3: Objective Function Computation using: f ( X ) , X = ( x 1 , , x N ) T .

Step 4: Iterative FA parameter definition for attractiveness (β), randomization (α) and coefficient of light absorption (γ).

Step 5: Firefly attraction, in which attractiveness depends on distance, such that: d a , b exp [ γ d a , b 2 ] .

Step 6: Light Intensity Update as per the created and computed solution.

Step 7: Limiting violation to both inequality and equality constraints.

Step 8: finding current best out of rated fireflies.

Step 9: Report result.

Step 10: Screen printout optimum solution based on firefly with highest light intensity.

Step 11: time plotting of iterations/time vs., light intensity.

Step 12: Stop.

Application of this pseudo code to the formulated problem is illustrated in the diagram of Figure 1.

Figure 1. Application of firefly algorithm to the formulated problem.

3.2. Data for the Formulation Model Simulation

The data for the firefly algorithm coding utilized a radial network. This network has values including: downstream load power demands symbolized as d, distances where transformers are placed and their kVA values, the reliability ratings of each line and is based on power demand of the section.

1) Network Zones and Parameters

For each of the nine zones, three parameters are considered for data inputs, as tabulated in Table 2. These include maximum kVA, downstream network length (km) and line failure rates.

2) Fault Location Time for 9 Zones

Once a faulty occurs on the downstream network, it takes time for the system to detect and locate. The data in Table 3 shows the time taken by system, to locate the faults.

Table 3 and Table 4 values were used to develop matrices for reclosing coefficient. Reclosing coefficient values were useful for optimization technique developed in firefly algorithm. Basically, all the zones’ distances are stretched for different kilometers along the network. Fault location and clearing time are solved using Equations (11) and (13) respectively. At first, fault location and clearing times are shorter and increases downstream. As long as the recloser is closer to the upstream distribution system, it is made to have a shorter time to locate and clear the fault once it occurs along the proposed radial line.

Table 2. Proposed network parameters.

Table 3. Fault location time along the radial line.

Table 4. Fault clearing time along the radial line.

4. Simulated Results and Discussions

4.1. Summary of Results

Tabulated results (Table 5), have each column’s input variables, as per the model system of radial network. Levels of reliability are inversely proportional to zonal span. Distance depended detection-period, for faults establish the clearance times in which distance is referenced to location of upstream recloser. This criterion implies longer clearing periods for furthest zone 9. Zone 9 has higher CENS, as compared to zone 8 that possesses less operation, maintenance and kVA * t costs, hence lowering the cost savings. A methodology to evaluate the economic advantages of using reclosers in power distribution system permitting. Self-operative procedures were discussed in [9].

The economic advantage contradicted the capital and the operational consumptions against the investment funds because of the decrease with the expense of energy not served. The use of a single recloser was obviously expensive compared to using two. The cost of capital investment for several reclosers became much beneficial to an extent that 40% of power was saved in a techno-economic assessment. Simulated result in this work realized a higher benefit of 43.3%.

4.2. Unserved Energy Cost-Savings

During power outages, derivation of equations based on un-served energy gives sufficient problem formulation for non-technical losses. Animal based power interruptions and illegal tapings contribute to transients causing blackouts. The plotted results of unserved energy cost savings is illustrated in Figure 2. These results indicate downstream CENS, with automatic optimization of upstream reclosing, as per the scheme of protection modeled in Equation (2). The plots imply that power transfer for upstream loads is higher in each zone.

Table 5. Summary of results.

Figure 2. Unserved energy costs.

4.3. Recloser Optimization, Distributed in 3D

Difference in cost of un-served energy varies from zone 1 to zone 9, based on simulated models, with significant variations. Figure 3 illustrates 3D distribution of cost of energy not served and demand distribution, in same plot. Both maximum and minimum values are illustrated for reclosed feeder zones, according to the simulation, as opposed to generation of un-served energy costs.

4.4. Validation of Results

To attest on results generated in this work, the reviewed publication [11] had a 40% savings for recloser placement. This previous work demonstrated recloser placement in a rural distribution network with a radial setting. Tradition formulation, recloser placement developed was on two levels. The problem was to optimize recloser placement. The first level, recloser allocation was reliability estimation of SAIFI and CAIDI in smaller areas within the feeder network. Estimation of reliability indices was on assumption that customers were evenly distributed. To some extent, second level placement was exact location employing simulation technique based on Roy Billiton Test System (RBTS).

In [15], optimal recloser placement in fault condition was based on design to cost methodology. The formulation was based on matrix tables available which could be used to determine maximum number of reclosers in the network. Cost benefit analysis was done and payback was possible within a yearly period. The results were that cost benefit factor was greater than 1 (one). This translated to benefit greater than cost when reclosers were distributed in a radial system.

Having analyzed these two techniques, the proposed technique appears to be an improvement in comparison. 43.3% savings which could be calculated in

Figure 3. Reclosers’ distribution along the Line (1 and 9 only).

every interruption is a better idea. The cost benefit analysis which runs for a year could be tedious work compared to the proposed method so far. This cost benefit factor kept the real unknown.

5. Conclusions

Cost of outages reduced as reclosers location moved away from substation, as per the analysis of realized results. Cost-Savings i.e. CENS were attained with minimization of zones, due to avoidance of multiple-outages. Reclosures were useful instead of either fuse or switch, which lead to prolonged outages, and the increased allocation and placement of CENS Reclosing can be achieved satisfactorily with the firefly algorithm simulation with optimum reclosing technique. CENS savings were achieved as predicted. Measure of success of the deployed technique is judged on basis of difference between minimum values of CENS and total cost.

In the future, it is possible to continue optimizing the recloser utilizing FA on harsh limitations, and inclusion of topologies for network. The mathematical technique used to optimize the reclosure placement was based on the CENS value. It has been found that the firefly algorithm has an effect on the reclosing ability of the feeder according to the cost of the process. The firefly algorithm has been effective in placing reclosers according to the regional energy cost not served.

Conflicts of Interest

The authors declare no conflicts of interest regarding the publication of this paper.

References

[1] Liu, W. and Huang, A.Q. (2005) A Novel High Current Solid-State Power Controller. 31st Annual Conference of IEEE Industrial Electronics Society, Raleigh, 6-10 November 2005, 5.
https://doi.org/10.1109/IECON.2005.1569094
[2] Qin, Q. and Wu, N.E. (2015) Recloser Allocation and Placement for Rural Distribution Systems. 2015 IEEE Power & Energy Society General Meeting, Denver, 26-30 July 2015, 1-5.
https://doi.org/10.1109/PESGM.2015.7286412
[3] Ovadia, S. (2004) Ratings and Rankings: Reconsidering the Structure of Values and Their Measurement. International Journal of Social Research Methodology, 7, 403-414.
https://doi.org/10.1080/1364557032000081654
[4] Perez, E.H., Nkanka, B.N., Ngulumingi, C.V., Gimeno, A. and Kazadi, A.B. (2005) Analysis of Technical Losses in Distribution Networks of Large Cities in Underdeveloped African Countries (Case of the City of Kinshasa/Dem. Rep. of Congo). 2005 IEEE Power Engineering Society Inaugural Conference and Exposition in Africa, Durban, 11-15 July 2005, 92-96.
[5] Chauhan, A.A. (2015) Non-Technical Losses in Power System and Monitoring of Electricity Theft over Low-Tension Poles. 2015 2nd International Conference on Advances in Computing and Communication Engineering, Dehradun, 1-2 May 2015, 280-284.
https://doi.org/10.1109/ICACCE.2015.106
[6] Adly, A.R., El Sehiemy, R.A. and Abdelaziz, A.Y. (2017) An Optimal/Adaptive Reclosing Technique for Transient Stability Enhancement under Single Pole Tripping. Electric Power Systems Research, 151, 348-358.
https://doi.org/10.1016/j.epsr.2017.06.005
[7] Blair, J., Hataway, G. and Mattson, T. (2018) Solutions to Common Distribution Protection Challenges. 2018 IEEE Rural Electric Power Conference (REPC), Memphis, 6-9 May 2018, 81-91.
https://doi.org/10.1109/REPC.2018.00021
[8] Álzate, A., Montoya, O.D., Hincapié, R.A. and Granada, M. (2015) Optimal Location of Reclosers in Distribution Systems Considering Reliability in Communication Channels. 2015 IEEE 6th Latin American Symposium on Circuits & Systems (LASCAS), Montevideo, 24-27 February 2015, 2-5.
https://doi.org/10.1109/LASCAS.2015.7250487
[9] Bansal, R. (2019) Power System Protection in Smart Grid Environment. CRC Press, Boca Raton, 519-550.
https://doi.org/10.1201/9780429401756
[10] Christopoulos, C. and Wright, A. (2013) Electrical Power System Protection. 2nd Edition, Springer, Boston.
https://doi.org/10.1007/978-1-4757-5065-2
[11] Niaz Azari, R. (2017) Optimal Recloser Setting, Considering Reliability and Power Quality in Distribution Networks. American Journal of Electrical Power and Energy Systems, 6, 1-6.
https://doi.org/10.11648/j.epes.20170601.11
[12] Yorukoglu, S., Nasibov, F., Mungan, M. and Bagriyanik, M. (2016) The Effect of the Types of Network Topologies on Non-Technical Losses in Secondary Electric Distribution Systems. 2016 IEEE/IAS 52nd Industrial and Commercial Power Systems Technical Conference (I&CPS), Detroit, 1-5 May 2016, 1-14.
https://doi.org/10.1109/ICPS.2016.7490218
[13] Liu, G., Yang, H., Kong, X. and Wen, S. (2018) Research on Positioning the Fault Locations Automatically in a Multi Branch Transmission Line Network. 2018 International Conference on Power System Technology (POWERCON), Guangzhou, 6-8 November 2018, 3099-3104.
https://doi.org/10.1109/POWERCON.2018.8602215
[14] Costa, M., Josken, J.V. and Walder, D.A. (2015) Fault Hunting Using Three-Phase Reclosers. 2015 IEEE Rural Electric Power Conference, Asheville, 19-21 April 2015, 17-21.
https://doi.org/10.1109/REPC.2015.19
[15] Strydom, R. and Hertzog, P.E. (2019) Recloser Placement on Medium Voltage Distribution Networks. 2019 Southern African Universities Power Engineering Conference/Robotics and Mechatronics/Pattern Recognition Association of South Africa (SAUPEC/RobMech/PRASA), Bloemfontein, 28-30 January 2019, 305-309.
https://doi.org/10.1109/RoboMech.2019.8704784

Copyright © 2024 by authors and Scientific Research Publishing Inc.

Creative Commons License

This work and the related PDF file are licensed under a Creative Commons Attribution 4.0 International License.